Commencement of operation for "Iwaki Yotsukura Wind Farm"
January 14, 2025
Hokutaku Co., Ltd. (Headquarters: Asahikawa City, Hokkaido, Representative Director: Ryuta Hayashi) started operation of the "Iwaki Yotsukura Wind Farm" since December 26, 2024 which had been under construction.
The power plant is a wind power generation facility with an output scale of 1,970 kW, and has been preparing for the start of operation since February 2022 with the aim of training maintenance personnel, demonstration tests of prototype parts produced at the research facility, and testing advanced technology development in collaboration with local companies.
With the support of local residents, we will continue to strive for secure and safe operation of power plants and contribute to the creation of a sustainable society through renewable energy.

1. Outline of the Project
Name of power plant | Iwaki Yotsukura Wind Farm |
---|---|
Name of operating company | Hokutaku Co., Ltd. |
Location | 77-24 Aza-Yoshinosawa, 297-2 Tado, Yotsukura-cho, Iwaki-shi, Fukushima |
Power Generation Capacity | Wind power: 1,970 kW * GOLDWIND _GW109/2.5MW x 1 * Controls the power plant output within 1,970 kW |
Annual Power Generation | Approx. 4,332,000 kWh/year * Equivalent to the annual power consumption of approximately 1,037 ordinary households |
CO2 reduction | Approx. 2,253 tons/year |
Construction period | February 2022 - December 2024 |
Operation start date | December 26, 2024 |
Power sold to | Tohoku Electric Power Company |
2. Location map of the power plant